Thursday, December 23, 2010

Internal fitout

The tiler has been and installed the tiles, its great to see the trades come through - I beleive the plumber has been out there to install the fittings for the bathrooms.  Paul managed to source some lovely camphor laurel to finish off the top plates for the living room and the bench seats in each of the rooms.

Internals


From the loft looking out towards the east - you can see some of the camphor laurel board


Spiral staircase to the loft - beyond that you can see one of the bench seats


Goin up to the loft

Main Bathroom


Breezeway looking down to Ollie's bedroom


The Laundry

Getting closer

Since we moved out of the rental we lost the camera charger so we were unable to get any good photos - of course we found the charger after we had bought a new one.... Murphy's law!!
We went out last Saturday to have a look at the progress. The guys have started cobbing for the first coat of render, the rain is playing havoc with the schedule and consequently the house is not going to be ready until early feb.  Cath and I are very dissapointed, but when it rains as much as it has been doing there is not a lot that can be done.
Some pics of the outside...


This is the back of the house with the first coat of render on


Front of the house


Master Bedroom with the railing starting to go up


Looking at the master bedroom door and  entry to the bathroom

Monday, November 22, 2010

It's called 'enclosed'

It's been a busy old time for the three of us - finalising moving, getting organised, and putting wood on steel joists.
We went out a couple of times to fix the cleats on the joists but we did not get them finished in time.  I found it hard to work if Ollie wasn't settled, and though I'm not making him my excuse I did find it hard going.
Cath and I can't believe we are getting closer to the finish.  We went out to speak to Paul last night and we should see some tiling early next week, flooring next week, then after that maybe some mud on the straw.  It will be hard being in Canberra and knowing that things will still be kicking along - I think we are both looking forward to some chill time - once we are back we will have a lot of painting and fencing to do.

Latest photos

Finished deck out of the main bedroom - just needs squaring off

Cath and Ollie hanging out on the deck

 Decking on the right breezeway completed

Outside loft completed - windows and louvres are in.

Sunday, October 31, 2010

update from the house site

I went out over the weekend to check the place out (without Cath cause the car is broken and the only one with a car seat) and took some snaps on the progress.  They are making good progress with the exterior cladding and the sliding doors are in.  We will be out there one the weekend (car permitting) so we can finish the cleats and tidy up behind the shed in prep for all the gardening equipment to come out there.  We worked out we have about 8 weekends before we go to Canberra and there are a lot of things that need to be done from our side.





Hoping that Paul will start trimming up the walls so we can get going with the cobbing

Sunday, October 24, 2010

Installing cleats

When we went back to Paul and asked him to quote for the whole job there were a couple of things we excluded.  Preparing the soil (which with all this rain has become a major headache - hopefully resolved by the stuff that was taken out of the biolytix hole).  The sanding and finishing of all floors, and installing cleats to the steel joists.  We decided that screwing the decking to the steel would take too long and was valuable labour time we did not want to spend.  We came up with the idea of installing pieces of timber along the joists so the decking can then be nailed to the timber - making it a quicker process.  This will also make the decking hopefully end up in line with the internal flooring making it seamless.... well that's the theory anyway




Site Supervisor - you just gotta have them!

Thanks to everyone that came out on the weekend to help - we managed to get all done bar the pool table area and the northern breezeway - and that was because the doors and scaffolding were on them.  We'll get back out there this weekend and hopefully some of the decking will be down.

Biolytix, Kitchen is in

With the first dry week for a long time occurring we have been able to get the Biolytix installed and the irrigation in place.  This filters all Grey and Black water from the house without having to worry about a separate system. 


The irrigation area is closer to the shed than I thought, but Rod has built up around it and once we move all the soil from the bottom of the envelope up to the fence ( creating an area so water will flow away from the house) then we should not have an issue with run off.  We will plant some shrubs in the are to help soak up the water and a week after we move in Rod will come back and put the worms in.

We also had the kitchen installed.  A little earlier than we wanted, but we had no choice as we had to line up with the kitchen's schedule.


We are really happy with the look of the kitchen - Paul assures me that the proximity of the end near the straw is not going to cause any dramas with the rendering process.  If it does become an issue then we may put gyprock where the kitchen buts up against the straw.


The island bench looks really great - though it is a pity that I wont be able to cut directly on the surface - but I will just make a big board to cover the area.


One thing that did come to light is that the depth of the fridge space is too shallow - Lucky we picked it up now and not when we were moving in!!!  Paul said it can be fixed... cheaper than the cost of a new fridge I hope.

Wednesday, October 13, 2010

straw is in

All the straw is up and complete - compression is under way. We went out there last weekend and took some photos
Granny flat outdoor area

2nd Bedroom, bathroom, master bedroom

Looking North, 2nd room, bathroom - you can see the bath

Kitchen, living room wall - spiral staircase up to loft

From the master bedroom there will be sliding doors through to the living room


Outdoor area.
The Electrician and Plumber have roughed in, materials are onsite for flooring, decking.  I think its a push now to get the kitchen ready as that will be the next thing to get in - doors and windows should be arriving soon....

Thursday, September 30, 2010

Straw Has Started!!!!

What a surprise to find that the straw has started - found out later that the engineer wants to see the tie downs as part of the framing certificate so its up with the straw.  It is kind of a bittersweet moment - something that Cath and I have schooled up on and wanted to really do ourselves is now not an option - but that's the way it goes.  Hopefully we will be able to do some cobbing as I'm sure Paul does not want to be left with all of that.

Start of the living room wall.  When they moved the straw from under the tarps where it has been for 12 months there was some trepidation as to what was living there.  We already knew there was a Red Belly (thank you Baxter the dog) but what else?  Thankfully the boys only saw a couple of field mice, but the worker in the shed had a meeting with afformentioned snake when it bolted out of the straw and into the shed!! 

Paul making a start on the Nothern Living room wall.  Some of the straw has been lost to the weather and a few of them will need to be handled carefully as the string has relaxed a bit - but it aint gonna fall down - not once the tie downs are there.


Pile of straw waiting to be put in


Electrician has already roughed in so hopefully those snap decisions we made on Wednesday will work out.
Solar Panels today - plumber on Monday....

Framing along

We went out there last week to see some of the framing and bracing on around the rooms - we had a quick dash over to the bathroom place to select a bath so we needed to see if the one we wanted will fit in the space.  We will have to back over the bathroom list so we can see if the other stuff will fit.

This is looking at Ollie's room- bracing done and the window starting to be framed.




The bathroom framing has started - with the toilet being framed.  We also have the the framing done for the walk in robe.





The kitchen with the window framing done.  This window is going to be a sliding window and screen allowing for this to be used as a servery



Cath and Ollie looking out of the ensuite.




Additions to the dam.  Where possible we are going to try non chemical ways of dealing with with different issues with the block - one big issue is the mosquitos - so we bought 20 Pacific Blue eye and put them in the dam, with the hope that they will bring down the Mosquito population.


Wednesday, September 22, 2010

And the rest of the roof is up

So we went out the week before last and we have the roof done. They have also cracked on with getting the framing completed.

This shows Oliver's room - you can also see the framing has started for the master bedroom.

From the front - Cath and Oliver having a sit - you can see the framing for the loft is almost complete.

View up from the living room looking out to the east.  This is how the living room roof will look.  The framing for the sliding doors can be seen below and they have also framed for the louvres and windows.

From the living room looking up to the loft they have framed for the storage room on the left and at the front you can see that the frame for the railing has been done - where there is no rail is where the spiral staircase will go.

This is looking from the South.

So its all starting to get a crack on - spoke to the builder last night and Paul said the kitchen people are keen to get their stuff done and he expects that we will have a kitchen in 4 weeks!  Also means that gyprock and flooring will also have to be done.  We will go out there this weekend to hopefully see most of the framing done.

Makes us both happy when we go out there and see progress - the house has a presence... and I think that with the position of the road where you wont really see the house until you turn the corner will work really well.
Cath and I are keen to get started - we have the permaculture plan and we hope to start building gardens in the next month - but not before we overcome the elephant (or should I say mud )  in the room.  We have to sift the clay to get it ready for rendering.  And as each day brings rain I just hope we haven't left our run too late for this....

Sunday, September 12, 2010

Half the roof is on

Since the build has started again there has been a flurry of activity as Paul pushes to get the roof on before the storm season starts up. We went out there a couple weekends ago and there was good progress.  So last weekend we arrive to see that half the roof is on!.  This photo is taken of the northern end so the granny flat and the outdoor area.  You can also see the ampelite sheeting that will sit over the outdoor dining area.



This is from the western side and you can see over to the right that there are still battens to put in.  You can also see the trusses for Oliver's room in the foreground and some wall framing for the master bedroom.


You can see here the insulation sitting between the roof and zincalume - this will be the finished look with the cross beam, exposed rafters and zincalume sheeting.

View from the loft looking out to the east.  Again, this is what the roof will look like - from the loft we will also see some of the view as above the sliding doors there are three panels of clear glass.