Tuesday, February 9, 2010

Posts are Up

Anyone who has been following the weather will have noticed a lot of rain up here - kind of turned the site into a quagmire - but in between falls we got the poles up!

We have 9 poles that form the basis of the build - these came from Grafton! The steel for the posts has also been delivered and hopefully in the next week these will be made a put in the ground - all 46 of them. For a green house there is a fair amount of concrete going into it - but there is not a lot we can do. Once a plot has been labelled (firezone, reactive soil, flood) you pretty well have to comply with all the regs that come with it. People say to check these things before you build, but realistically unless you have a lot of money - the land that has none of these constraints are pretty expensive. Thankfully the changes we have had to make to the design, and the materials has not been too great....

No comments:

Post a Comment